I am please to report that renovation work on the pavilion at the bowling green is well under way.
This is how it looked at the end of 2009.
20th February. An access ramp has been installed from the gate into Ashworth Road, and the old roof is being removed.
27th February: The old roof has gone, and the inside has been gutted.
9th March: A temporary roof covering is in place.
26th March: New roof material is fitted...
26th March: ... and a waterproof membrane is installed.