Saturday, 15 May 2010

Bowling Green Pavillion Renovation Completed

1st April: Roof nearing completiong.
6th April: Roof complete.  New walls built in front of building.
 24th April.Scaffolding removed.
26th April.  Window frames arrive ...
... and are fitted
30th April: Double glazing fitted.
12th May: Internal fit out nearly complete.  Furniture arrives.
15th May: Complete and ready for the official opening later the same day.