1st April: Roof nearing completiong.
6th April: Roof complete. New walls built in front of building.
24th April.Scaffolding removed.
26th April. Window frames arrive ...
... and are fitted
30th April: Double glazing fitted.
12th May: Internal fit out nearly complete. Furniture arrives.
15th May: Complete and ready for the official opening later the same day.